Engineering & Technical Coordination
Overview
The Engineering & Technical Coordination process at BEC Arabia ensures that all subcontractors comply with technical requirements, project specifications, and design standards. This structured approach guarantees that subcontractor work integrates seamlessly with project execution while maintaining quality, safety, and efficiency.
This process is designed to:
Ensure subcontractors follow approved technical specifications
Facilitate smooth coordination between subcontractors, project teams, and consultants
Streamline the submission and approval process for RFIs, technical submittals, and shop drawings
Ensure compliance with KSA regulations, international standards, and project-specific requirements
Minimize rework and delays caused by misalignment in technical execution
Key Stakeholders
β Engineering & Technical Teams β Review, approve, and coordinate technical submittals and shop drawings β Project Management Team β Oversees subcontractor interface and ensures timely execution β QA/QC Team β Ensures subcontractor work meets technical and quality standards β Procurement Team β Ensures materials meet approved specifications before procurement β Consultants & Client Representatives β Provide final approvals on design and engineering aspects
Step-by-Step Engineering & Technical Coordination Process
π 1. Submittal & Approval of RFIs and Technical Documents
Before starting any work, subcontractors must submit technical documents for review and approval. These include:
Request for Information (RFI) β Used when subcontractors require clarifications on designs, specifications, or execution details
Shop Drawings β Detailed drawings that show how subcontractor work integrates with the project
Material Submittals β Documentation proving that materials comply with project requirements
Method Statements β Step-by-step procedures explaining how specific work will be executed
π Template: RFI Submission Form
π 2. Technical Review & Approval Workflow
Once subcontractors submit their technical documents, the approval workflow follows a structured process:
Stage
Responsible Party
Review Focus
Timeline
Initial Review
Engineering Team
Technical specifications & compliance
3 Days
QA/QC Review
QA/QC Team
Quality control & site execution feasibility
2 Days
Consultant Approval
Client/Consultant
Final validation against project requirements
5 Days
If revisions are required, subcontractors must submit a resubmission with the requested modifications.
π Template: Technical Submittal Review Form
π 3. Coordination of Shop Drawings and Technical Approvals
Shop drawings are crucial for site execution and must align with approved project drawings. The coordination process includes:
Subcontractor submits shop drawings for approval
Engineering team checks alignment with design intent
QA/QC team verifies constructability and quality compliance
Consultant provides final review and approval
Approved shop drawings are issued for site execution
Subcontractors are not allowed to proceed with work until shop drawings are fully approved.
π Template: Shop Drawing Submission Form
π 4. Site Coordination & Subcontractor Interface Management
Effective site coordination ensures that multiple subcontractors work together efficiently without clashes or delays. The Project Engineering Team oversees:
Coordination Meetings β Weekly technical meetings with subcontractors to resolve conflicts and align execution plans
Site Work Sequencing β Scheduling subcontractor work to prevent overlapping activities
Clash Detection & Resolution β Using Building Information Modeling (BIM) or site inspections to detect technical clashes early
Interface Coordination β Managing dependencies between different subcontractors, such as MEP, structural, and finishing teams
If subcontractors fail to comply with approved shop drawings or execution plans, corrective actions are issued.
π Template: Subcontractor Coordination Meeting Minutes
π 5. Material Submittals & Inspection Process
Before using any materials on-site, subcontractors must submit Material Approval Requests to verify compliance.
Material Submittal Process:
Subcontractor submits material samples & datasheets
Engineering team reviews compatibility with project requirements
QA/QC team inspects quality standards
Consultant provides final material approval
Procurement team processes material orders
Only approved materials can be used in project execution.
π Template: Material Approval Request Form
π 6. Managing Engineering Changes & Technical Disputes
During execution, subcontractors may encounter unforeseen technical challenges requiring design modifications.
Common cases include:
Design conflicts detected on-site
Unavailability of specified materials
Changes in site conditions requiring engineering adjustments
π Change Management Process:
β Step 1: Subcontractor submits a Change Request Form β Step 2: Engineering team assesses the impact and provides recommendations β Step 3: Consultant reviews and issues approval/rejection β Step 4: If approved, a Change Order is issued and updated shop drawings are provided
π Template: Engineering Change Request Form
7. Risk Management in Engineering & Technical Coordination
To mitigate risks related to technical execution, BEC Arabia enforces strict risk assessment procedures:
Risk Type
Mitigation Strategy
Design Discrepancies
Conduct detailed design reviews before execution
Delayed Approvals
Implement fast-track approval processes for critical work
Incorrect Material Usage
Require pre-approval of all materials before ordering
Clash Between Trades
Conduct BIM clash detection and weekly coordination meetings
Subcontractor Execution Errors
Enforce strict quality inspections and rework penalties
If subcontractors fail to meet engineering compliance, penalties or corrective actions are applied.
π Template: Subcontractor Non-Conformance Report
Documentation & SharePoint Storage
All technical documents, RFIs, and approvals must be stored in the Engineering SharePoint Folder for tracking and compliance.
π Key Documents Stored in SharePoint
Document
Purpose
Access Link
RFI Logs
Tracks all subcontractor technical queries
Open Folder
Approved Shop Drawings
Ensures subcontractors follow correct execution plans
Open Folder
Material Approvals
Confirms all materials meet project standards
Open Folder
Engineering Change Requests
Documents approved modifications in design
Open Folder
Coordination Meeting Records
Tracks subcontractor interface discussions
Open Folder
Final Notes & Key Takeaways
All subcontractors must submit RFIs, shop drawings, and material approvals before work starts
Engineering teams must review all submittals within defined approval timelines
Weekly coordination meetings must be conducted to prevent execution clashes
Material inspections must be conducted before installation to ensure compliance
Engineering changes must go through formal approval to avoid unauthorized modifications