Engineering & Technical Coordination

Overview

The Engineering & Technical Coordination process at BEC Arabia ensures that all subcontractors comply with technical requirements, project specifications, and design standards. This structured approach guarantees that subcontractor work integrates seamlessly with project execution while maintaining quality, safety, and efficiency.

This process is designed to:

  • Ensure subcontractors follow approved technical specifications

  • Facilitate smooth coordination between subcontractors, project teams, and consultants

  • Streamline the submission and approval process for RFIs, technical submittals, and shop drawings

  • Ensure compliance with KSA regulations, international standards, and project-specific requirements

  • Minimize rework and delays caused by misalignment in technical execution

Key Stakeholders

βœ… Engineering & Technical Teams – Review, approve, and coordinate technical submittals and shop drawings βœ… Project Management Team – Oversees subcontractor interface and ensures timely execution βœ… QA/QC Team – Ensures subcontractor work meets technical and quality standards βœ… Procurement Team – Ensures materials meet approved specifications before procurement βœ… Consultants & Client Representatives – Provide final approvals on design and engineering aspects


Step-by-Step Engineering & Technical Coordination Process

πŸ“‚ 1. Submittal & Approval of RFIs and Technical Documents

Before starting any work, subcontractors must submit technical documents for review and approval. These include:

  • Request for Information (RFI) – Used when subcontractors require clarifications on designs, specifications, or execution details

  • Shop Drawings – Detailed drawings that show how subcontractor work integrates with the project

  • Material Submittals – Documentation proving that materials comply with project requirements

  • Method Statements – Step-by-step procedures explaining how specific work will be executed

πŸ“Œ Template: RFI Submission Form


πŸ“‚ 2. Technical Review & Approval Workflow

Once subcontractors submit their technical documents, the approval workflow follows a structured process:

Stage

Responsible Party

Review Focus

Timeline

Initial Review

Engineering Team

Technical specifications & compliance

3 Days

QA/QC Review

QA/QC Team

Quality control & site execution feasibility

2 Days

Consultant Approval

Client/Consultant

Final validation against project requirements

5 Days

If revisions are required, subcontractors must submit a resubmission with the requested modifications.

πŸ“Œ Template: Technical Submittal Review Form


πŸ“‚ 3. Coordination of Shop Drawings and Technical Approvals

Shop drawings are crucial for site execution and must align with approved project drawings. The coordination process includes:

  • Subcontractor submits shop drawings for approval

  • Engineering team checks alignment with design intent

  • QA/QC team verifies constructability and quality compliance

  • Consultant provides final review and approval

  • Approved shop drawings are issued for site execution

Subcontractors are not allowed to proceed with work until shop drawings are fully approved.

πŸ“Œ Template: Shop Drawing Submission Form


πŸ“‚ 4. Site Coordination & Subcontractor Interface Management

Effective site coordination ensures that multiple subcontractors work together efficiently without clashes or delays. The Project Engineering Team oversees:

  • Coordination Meetings – Weekly technical meetings with subcontractors to resolve conflicts and align execution plans

  • Site Work Sequencing – Scheduling subcontractor work to prevent overlapping activities

  • Clash Detection & Resolution – Using Building Information Modeling (BIM) or site inspections to detect technical clashes early

  • Interface Coordination – Managing dependencies between different subcontractors, such as MEP, structural, and finishing teams

If subcontractors fail to comply with approved shop drawings or execution plans, corrective actions are issued.

πŸ“Œ Template: Subcontractor Coordination Meeting Minutes


πŸ“‚ 5. Material Submittals & Inspection Process

Before using any materials on-site, subcontractors must submit Material Approval Requests to verify compliance.

Material Submittal Process:

  1. Subcontractor submits material samples & datasheets

  2. Engineering team reviews compatibility with project requirements

  3. QA/QC team inspects quality standards

  4. Consultant provides final material approval

  5. Procurement team processes material orders

Only approved materials can be used in project execution.

πŸ“Œ Template: Material Approval Request Form


πŸ“‚ 6. Managing Engineering Changes & Technical Disputes

During execution, subcontractors may encounter unforeseen technical challenges requiring design modifications.

Common cases include:

  • Design conflicts detected on-site

  • Unavailability of specified materials

  • Changes in site conditions requiring engineering adjustments

πŸ“Œ Change Management Process:

βœ” Step 1: Subcontractor submits a Change Request Form βœ” Step 2: Engineering team assesses the impact and provides recommendations βœ” Step 3: Consultant reviews and issues approval/rejection βœ” Step 4: If approved, a Change Order is issued and updated shop drawings are provided

πŸ“Œ Template: Engineering Change Request Form


7. Risk Management in Engineering & Technical Coordination

To mitigate risks related to technical execution, BEC Arabia enforces strict risk assessment procedures:

Risk Type

Mitigation Strategy

Design Discrepancies

Conduct detailed design reviews before execution

Delayed Approvals

Implement fast-track approval processes for critical work

Incorrect Material Usage

Require pre-approval of all materials before ordering

Clash Between Trades

Conduct BIM clash detection and weekly coordination meetings

Subcontractor Execution Errors

Enforce strict quality inspections and rework penalties

If subcontractors fail to meet engineering compliance, penalties or corrective actions are applied.

πŸ“Œ Template: Subcontractor Non-Conformance Report


Documentation & SharePoint Storage

All technical documents, RFIs, and approvals must be stored in the Engineering SharePoint Folder for tracking and compliance.

πŸ“‚ Key Documents Stored in SharePoint

Document

Purpose

Access Link

RFI Logs

Tracks all subcontractor technical queries

Open Folder

Approved Shop Drawings

Ensures subcontractors follow correct execution plans

Open Folder

Material Approvals

Confirms all materials meet project standards

Open Folder

Engineering Change Requests

Documents approved modifications in design

Open Folder

Coordination Meeting Records

Tracks subcontractor interface discussions

Open Folder


Final Notes & Key Takeaways

  • All subcontractors must submit RFIs, shop drawings, and material approvals before work starts

  • Engineering teams must review all submittals within defined approval timelines

  • Weekly coordination meetings must be conducted to prevent execution clashes

  • Material inspections must be conducted before installation to ensure compliance

  • Engineering changes must go through formal approval to avoid unauthorized modifications