Performance & Compliance

Subcontractor Performance & Compliance

Overview

The Subcontractor Performance & Compliance framework ensures that all subcontractors engaged by BEC Arabia consistently meet contractual obligations, maintain quality standards, adhere to safety regulations, and comply with KSA laws. This structured approach helps minimize risks, improve efficiency, and ensure that mega projects progress smoothly.

Performance monitoring allows BEC Arabia to:

Ensure subcontractors meet project timelines and quality expectations.Enforce HSE compliance and mitigate safety risks.Track subcontractor KPIs for long-term evaluation and future selection.Identify and resolve non-compliance issues early.Apply corrective measures or termination if performance does not improve.

Every subcontractor working on a BEC Arabia project is subject to regular evaluations and compliance audits to maintain project standards.


Step-by-Step Performance & Compliance Monitoring Process

1️⃣ Performance Monitoring Criteria

To assess subcontractor performance, BEC Arabia evaluates five key areas:

Performance Area

Evaluation Criteria

Responsible Department

Quality of Work

Adherence to project specifications, zero rework, defect-free delivery.

Engineering & QA/QC

Project Timelines

Completion of milestones as per schedule.

Project Management

HSE Compliance

No safety violations, proper site practices.

HSE Department

Financial Compliance

Adherence to contract payment terms, invoicing accuracy.

Finance

Workforce & Equipment Readiness

Adequate manpower, equipment availability, and mobilization efficiency.

Project & Procurement

Subcontractors receive monthly performance ratings, and those with a rating below 75% are flagged for corrective actions.


2️⃣ Monthly Performance Evaluation Reports

Each subcontractor is required to submit a Monthly Progress Report (MPR) detailing:

📌 Work completed & milestones achieved. 📌 Any delays or challenges faced. 📌 Workforce deployment & productivity. 📌 Equipment status & maintenance records. 📌 HSE performance & incident reports.

The Project Management Team reviews the reports and verifies actual performance on-site.

📌 Template: Monthly Subcontractor Performance Report


3️⃣ Compliance Audits & Safety Inspections

Subcontractors must undergo routine compliance checks to ensure they follow:

HSE regulations and site safety rules.Legal and financial compliance.Project quality standards and site protocols.

BEC Arabia conducts two types of audits:

Audit Type

Frequency

Responsible Team

Safety Compliance Audit

Bi-weekly

HSE Team

Work Quality & Progress Audit

Monthly

QA/QC & Project Team

Subcontractors failing two consecutive audits are subject to penalties, re-evaluation, or contract termination.

📌 Template: Subcontractor Compliance Audit Checklist


4️⃣ Handling Non-Compliance Issues

If a subcontractor fails to meet performance or compliance requirements, BEC Arabia follows a structured corrective action plan:

📌 Non-Compliance Process:

Step 1: Issue a formal warning letter specifying violations. ✔ Step 2: Give the subcontractor a defined period for corrective actions. ✔ Step 3: Conduct a follow-up compliance audit. ✔ Step 4: If unresolved, escalate to contract penalties or termination.

Non-Compliance Type

Corrective Action Timeline

Potential Consequences

Minor Safety Violations

48 hours to rectify

Warning letter, training requirement

Quality Issues

5-7 days to rework

Deduction from payments, additional supervision

Repeated Delays

14 days to implement mitigation

Liquidated damages, possible replacement

Major Contract Breach

Immediate resolution

Termination & financial penalties

📌 Template: Subcontractor Non-Compliance Report


5️⃣ Subcontractor Improvement Plans

If a subcontractor is underperforming but not at the stage of termination, BEC Arabia initiates a Subcontractor Improvement Plan (SIP):

📌 Improvement Plan Includes:

Clear corrective actions and deadlines.Additional training or site supervision.Weekly progress check-ins and evaluation.Performance re-evaluation after 30 days.

If the subcontractor fails to improve within 60 days, BEC Arabia may suspend new work orders or terminate the contract.

📌 Template: Subcontractor Improvement Plan


Special Cases & Escalations

🔹 Subcontractor Requests Deadline Extensions

❌ Issue: The subcontractor claims delays due to external factors (weather, material delays). ✅ Solution: ✔ Review justification with Project Team. ✔ If valid, issue a Time Extension Addendum. ✔ If not justified, apply contract penalties for late delivery.

📌 Template: Subcontractor Time Extension Request

🔹 Safety Violation by a Subcontractor

❌ Issue: The subcontractor has repeated HSE violations on-site. ✅ Solution: ✔ Issue a Safety Violation Notice. ✔ Conduct additional safety training. ✔ If the issue continues, suspend site access until resolved.

📌 Template: Subcontractor HSE Violation Report

🔹 Subcontractor Fails to Meet Payment Terms

❌ Issue: Subcontractor refuses to pay labor or suppliers. ✅ Solution: ✔ Escalate to Finance & Legal. ✔ Issue a Payment Non-Compliance Notice. ✔ Withhold project payments if necessary.

📌 Template: Subcontractor Payment Compliance Notice


Documentation & SharePoint Storage

All performance and compliance-related documents must be stored in the Subcontractor SharePoint Folder.

📁 Key Documents Stored in SharePoint

Document

Purpose

Access Link

Monthly Performance Reports

Tracks subcontractor work progress & compliance.

Open Folder

Compliance Audit Checklists

Records results of safety and quality audits.

Open Folder

Non-Compliance Reports

Documents violations and corrective actions.

Open Folder

Subcontractor Improvement Plans

Tracks underperforming subcontractors.

Open Folder

Final Performance Evaluation

Used for subcontractor future selection.

Open Folder


Final Notes & Key Takeaways

Performance tracking ensures subcontractors deliver as per contract.HSE, quality, and financial compliance are monitored monthly.Non-compliance is addressed through corrective actions or termination.All performance-related documents must be stored in SharePoint.

For inquiries, contact [email protected] or the Project Control Team.