Subcontractor Selection

Procurement & Subcontractor Selection

Overview

The Procurement & Subcontractor Selection process at BEC Arabia ensures that only the most qualified, financially stable, and compliant subcontractors are engaged for projects. This structured approach minimizes contractual, financial, and operational risks, ensuring successful project execution in alignment with BEC Arabia’s quality, safety, and commercial objectives.

This process is designed to:

  • Ensure fairness and transparency in subcontractor selection

  • Mitigate risks by prequalifying subcontractors based on financial, legal, and technical standards

  • Optimize cost efficiency by selecting the most competitive and technically capable subcontractors

  • Ensure compliance with KSA regulations, project requirements, and BEC Arabia’s procurement policies

The procurement process involves multiple stakeholders, including:

Procurement Team – Manages tendering, bid evaluations, and contract negotiations ✅ Project Management Team – Reviews subcontractor capabilities based on project needs ✅ Legal & Contracts Team – Ensures compliance with contractual and regulatory requirements ✅ Finance Team – Verifies subcontractor financial stability and payment terms ✅ HSE & QA/QC Teams – Ensures subcontractors meet safety and quality standards


Step-by-Step Procurement & Subcontractor Selection Process

📂 1. Identifying Subcontractor Requirements

Before initiating the procurement process, the Project Team provides the Procurement Department with the following:

  • Scope of work and project specifications

  • Estimated budget and cost parameters

  • Required certifications and compliance standards

  • Project timeline and subcontractor mobilization schedule

Once requirements are confirmed, the procurement team identifies potential subcontractors from the Approved Vendor List (AVL) or issues a prequalification process to assess new suppliers.


📂 2. Tendering & Bid Invitation Process

The procurement team issues a formal Request for Quotation (RFQ) or Request for Proposal (RFP) to prequalified subcontractors. This process includes:

  • Issuing bid documents with project scope, technical specifications, and submission deadlines

  • Conducting pre-bid meetings to clarify project requirements

  • Establishing a clear evaluation criteria, including technical, financial, and compliance factors

Subcontractors must submit:

  • Detailed technical proposal outlining work methodology

  • Financial proposal with cost breakdowns

  • Work experience and previous project references

  • HSE and quality compliance documentation

📌 Template: Request for Proposal (RFP) Template


📂 3. Bid Evaluation & Subcontractor Selection

Once bids are received, they are evaluated based on the following:

Evaluation Area

Criteria

Weightage

Technical Capability

Experience, resources, and ability to execute work

40%

Financial Proposal

Cost competitiveness and payment terms

30%

Compliance & HSE

Adherence to KSA laws and safety regulations

20%

Previous Performance

Past project success and client references

10%

The Procurement and Project Teams review the top-ranked subcontractors, conducting interviews or site visits if necessary.

📌 Template: Bid Evaluation Report


📂 4. Negotiation & Contract Finalization

After selecting the preferred subcontractor, the contract negotiation phase begins, ensuring:

✔ Finalized pricing, scope, and timeline agreements ✔ Review and inclusion of risk mitigation clauses ✔ Legal and financial due diligence completion ✔ Clarification of key contractual terms, including payment schedules, retention, and penalties

📌 Template: Subcontractor Contract Negotiation Checklist

Once all terms are finalized, the contract is signed and stored in SharePoint for tracking and compliance.


📂 5. Issuance of Work Orders & Mobilization

Upon contract execution, the subcontractor receives a Work Order (WO) outlining:

  • Project-specific instructions

  • Site mobilization requirements

  • Start date and key milestones

  • Safety and compliance guidelines

Project teams verify subcontractor mobilization readiness through:

✔ Submission of labor and equipment mobilization plans ✔ Completion of HSE induction and compliance training ✔ Submission of all technical submittals before work starts

📌 Template: Subcontractor Work Order Form


6. Risk Management in Procurement & Subcontractor Selection

To minimize procurement risks, BEC Arabia follows a structured risk assessment process:

Risk Type

Mitigation Strategy

Subcontractor Financial Instability

Require performance guarantees and advance payment bonds

Poor Quality Work

Enforce strict QA/QC approvals and penalties for defects

Safety Non-Compliance

Immediate suspension and financial penalties for violations

Delayed Work Execution

Apply liquidated damages for project delays

Each subcontractor must sign a Risk Acknowledgment Agreement, committing to BEC Arabia’s performance standards and compliance requirements.

📌 Template: Subcontractor Risk Acknowledgment Form


Common Procurement & Subcontractor Selection Issues and Solutions

Subcontractor Submits an Unclear or Incomplete Proposal

❌ Issue: Proposal lacks detail on execution methodology or cost breakdown. ✅ Solution: Request a proposal revision or eliminate the bidder from consideration.

Multiple Bidders Meet Selection Criteria

❌ Issue: Several subcontractors qualify for the project. ✅ Solution: Conduct an interview or site visit to determine the best fit.

Subcontractor Requests a Price Increase Post-Award

❌ Issue: Subcontractor claims increased material costs. ✅ Solution: Reject unapproved cost escalations unless a valid variation order is approved.

Subcontractor Fails to Mobilize on Time

❌ Issue: Delays in labor or equipment mobilization. ✅ Solution: Issue a Notice of Default and enforce contract penalties.

📌 Template: Subcontractor Default Notice


Documentation & SharePoint Storage

All procurement and subcontractor selection documents must be securely stored in the Procurement SharePoint Folder for reference and audit purposes.

📂 Key Documents Stored in SharePoint

Document

Purpose

Access Link

Prequalified Vendor List

Approved subcontractors database

Open Folder

Bid Evaluation Reports

Assessment of subcontractor proposals

Open Folder

Finalized Subcontractor Agreements

Signed contracts for each subcontractor

Open Folder

Work Orders & Mobilization Reports

Verification of subcontractor readiness

Open Folder

Risk Assessment Reports

Procurement risk mitigation records

Open Folder


Final Notes & Key Takeaways

  • All subcontractors must pass the bid evaluation and selection process before contract award.

  • All procurement-related documents must be stored in SharePoint for compliance tracking.

  • Subcontractor financial risks must be mitigated with guarantees and payment terms.

  • HSE and QA/QC compliance is a key factor in subcontractor selection.

  • Contract negotiations must include clear scope, payment, and penalty clauses.

For any procurement-related inquiries, contact [email protected] or the Contracts and Legal Team.