Estimation Department – Standardized Template

1. Project Overview

1.1 General Information

  • Project Name: [Enter Project Name]

  • Client Name: [Client/Employer]

  • Project Location: [City, Region, Country]

  • Project Type: [Infrastructure, Commercial, Residential, Industrial]

  • Contract Type: [Lump Sum, Unit Rate, Cost-Plus, EPC]

  • Estimated Project Duration: [Months/Years]

  • Tender Submission Deadline: [Date & Time]

1.2 Scope of Work

  • Main Deliverables: [Brief description of key work items]

  • BOQ (Bill of Quantities) Reference: [Attached Document Link]

  • Key Constraints & Requirements: [Special Conditions, Regulatory Needs]


2. Cost Estimation Breakdown

2.1 Direct Costs

Material Costs

  • Primary Materials: [Steel, Concrete, Asphalt, etc.]

  • Suppliers/Vendors Considered: [Vendor 1, Vendor 2]

  • Cost per Unit: [SAR or USD]

  • Total Cost Estimate: [SAR/USD]

Labor Costs

  • Skilled Labor Requirements: [Engineers, Supervisors, Technicians]

  • Unskilled Labor Needs: [General Workers, Helpers]

  • Labor Rate (Per Hour/Day): [SAR/USD]

  • Total Labor Cost: [SAR/USD]

Equipment Costs

  • Required Machinery: [Excavators, Cranes, Trucks]

  • Rental vs. Purchase Analysis: [Comparison Table]

  • Cost Per Unit: [SAR/USD]

  • Total Equipment Cost: [SAR/USD]

2.2 Indirect Costs

  • Overheads & Administration: [Office Costs, Permits, Security]

  • Site Facilities & Setup: [Temporary Offices, Worker Accommodation]

  • Utilities & Power Costs: [Electricity, Water]

  • Contingency & Risk Allowance: [5-10% as per project complexity]

2.3 Final Estimate Summary

Category

Estimated Cost (SAR/USD)

Materials

[Cost]

Labor

[Cost]

Equipment

[Cost]

Indirect Costs

[Cost]

Total Estimate

[Total Cost]


3. Risk Assessment & Mitigation Plan

3.1 Identified Risks

Risk Type

Likelihood (L/M/H)

Impact (L/M/H)

Mitigation Strategy

Cost Overrun

High

High

Detailed Cost Breakdown & Contingency Inclusion

Material Shortages

Medium

High

Long-Term Supplier Agreements & Market Analysis

Labor Productivity Fluctuation

Medium

Medium

Workforce Planning & Efficiency Monitoring

3.2 Contingency Allocation

  • Inflation Allowance: [2-5% of estimated cost]

  • Market Fluctuation Buffer: [Based on past trends]

  • Regulatory/Compliance Risks: [KSA Laws, Nitaqat Saudization]


4. Compliance & Approvals

4.1 Internal Approvals

Approver Name

Designation

Approval Status

BD Director

Business Development

Pending/Approved

Finance Head

Finance & Budgeting

Pending/Approved

Legal Counsel

Contract & Risk

Pending/Approved

CEO

Executive Decision

Pending/Approved

4.2 Regulatory Compliance Checklist

  • Etimad/NUPP Registration Status: [Yes/No]

  • PIF Compliance Requirements: [Met/Not Met]

  • Environmental & Sustainability Mandates: [Compliant/Non-Compliant]


5. Final Submission Package

5.1 Required Documents Checklist

β˜‘ BOQ & Cost Estimate Summary β˜‘ Bid Pricing Form β˜‘ Technical Proposal & Methodology β˜‘ Vendor Quotations & Market Benchmarking β˜‘ Risk Analysis & Contingency Plan β˜‘ Contractual & Compliance Documents β˜‘ Bid Submission Letter

5.2 Submission Confirmation

  • Date of Submission: [Date]

  • Submitted By: [Estimator Name]

  • Submission Portal: [Etimad, NUPP, Direct Client]

  • Acknowledgment Received: [Yes/No]


6. Post-Submission Monitoring & Lessons Learned

6.1 Follow-up & Negotiations

  • Client Clarifications Addressed: [Yes/No]

  • Negotiation Adjustments Required: [Pricing Revisions, Scope Changes]

  • Final Outcome: [Accepted, Rejected, Under Review]

6.2 Lessons Learned & Process Improvement

  • Deviation from Initial Estimate (%): [Variance Analysis]

  • Competitor Benchmarking Insights: [Pricing Competitiveness]

  • Enhancements for Future Estimations: [Software Upgrades, Additional Market Research]


7. Conclusion

This Estimation Department Template ensures that all cost estimations follow a structured, standardized, and compliant methodology at BEC Arabia. By maintaining accuracy, risk mitigation, and strategic financial planning, this framework supports the company’s competitive bidding success and profitability in Saudi Arabia’s construction industry.